Rubber Lining in Clarifier Tanks

Universal Blasto was subcontracted by Fisher Tank to replace an interior rubber lining on two clarifier tanks. The work needed to be completed simultaneously and in a timely manner.

PROJECT DETAILS

  • INDUSTRY: Coal-Fired Power Generation
  • LOCATION: South Carolina
  • YEAR: 2018
  • FOR MORE INFORMATION: Reference job S18-072
     
    rubber lining in clarifier tank

ABOUT THE TANKS

  • Two tanks completed simultaneously in 38 shifts
  • Elevated, open top clarifier tanks with sloped, scalloped floors, sump, trough and weir tabs
  • 35 feet in diameter

 

PROCEDURE

  • Installed Bonnet over top to control environmental conditions
  • Blasted the new carbon steel surface
  • Applied REMA 304 Primer
  • Applied REMA CHEMOLINE 4CN pre-vulconized rubber, using REMA SC4000 and BC3004 cements on the interior
  • Applied a three coat exterior system including zinc, epoxy and urethane coatings

 

In addition to rubber linings, Universal Blastco does blasting, coatings, FRP work, industrial masonry, inspections, concrete restoration and more. Request your free quote here, email blastco@isginc.us or call 803-773-6388.

Rubber application on the floor of a tank

Containment on roof of tank

Rubber lining on tank floor

rubber lining in a clarifier tank